Scheme 3, the Linton Greenway, has been divided into 5 sections. Sections 1 and 2 are already complete.
- Section 4 has been spilt into two phases of work, with phase 1 early works between Newmarket Road and Granta Park completed in autumn 2024.
- Section 5 of the greenway is also in progress, with sections of the active travel path between Hildersham and Linton already widened.
- Section 3 involves further design work on the bridge crossing the A11 and is due to start construction in 2025.
- The route would then continue on-road through the Abingtons to the Hildersham crossroads.